Real Time Construction Planned versus Actual Reporting
Key takeaways
Learn about how you can track planned versus actual progress in real time using your Gather site records.
Transcript
Hi, it's Will from Gather. Today I'm going to show you how to use your site diary to give you real-time commercial assurance.
0:13
Planned vs Actual
The graphs in front of you look nice and pretty. What they actually show is giving you planned and actual comparisons for costs from labour, plants, and hours worked as well. You can understand how that relates back to your overall forecast budgets and cost allocations.
Let's start with how it's built up. We get our information from our typical records — typical records, which is from step three in Gather on labour and materials. We can see here that it's built up, as you can see in front of us. We've got our people here, Nick, Joe, Alex and Elena, the role that they undertake and their supplier. This allows us to understand their rate.
We've got their shift times as well in step one. We can see when the shift starts and the duration of the shift. From this we know it's a midweek day, a weekend, midweek night, even a bank holiday or special rate.
We can also do the same for plant. We've got the suppliers again. We've got the materials being provided. We've got all that information here. That gives us our cost of work done for every single shift record.
Digging into the detail
Let's go back to our key insights. An example: here is our project overview. We can see got that plan cost. We've imported our planning. We forecast what we thought this project's going to cost. We've got our cumulative actual today as well. We can filter it by different weeks. But this is the overall project.
Digging into the detail, we can see we've got labour and the plant as well. We can see what we plan to spend on labour. So far, we are 97% of the budget through. So it's not looking too good. The plant is much, much lower. So yeah, you can start to see where those peaks and troughs are and that a lot of differences.
We can also do a comparison by hours worked. This is labour and plant together. We can filter it with just labour or plant as well. Again, we're quite far through our planned hours. It looks a little bit different to what we expected.
2:06
Interpreting trends
Going to this graph here, we can start to see the yellow line is accumulative plan costs, and accumulative actual costs. Quite interesting there. You might think: Oh, we're under budget. But commonly, when you see this sort of angle on a curve, you probably see this project's going a lot longer. You need to dig into it and start to see those spends.
We can use WBS, P6 Reference, to understand cost allocation by package, and that's really useful for us to do. We can start to see where we're spending our money.
Real-time CVR
When I was a QS, what I would have loved is to be able to do a real-time CVR. I can start to do that here. So let's filter for a particular week. Say, week commence 20 November. We can start to see plan versus actual: the planned hours, actual hours, and the total hours as well.
Do the same for plant. So we can start to see that sort of information again. We'll choose the same week for our particular plant groups — dumpers, dozers, that sort of things are all in there. What I quite like is our cost allocation, so we can start to see our actual costs against our planned cost profile. We can start to see where we're winning and where we're losing.
Have a look at this. It's available to everyone on the Gather platform. Just make sure you're capturing the labour, plant materials as we've got here. There you go.
Thank you for watching.
Stay ahead of the curve
Our monthly email newsletter keeps you up-to-date with best practices in project management, contech implementation and NEC contracts.